03 June 2020

The Court of Session have upheld an appeal by Gladman Developments Limited against the decision of a Reporter to dismiss their planning appeal for a residential development at Quarriers Village, Kilmacolm, Inverclyde.

Background

In 2014, ‘Scottish Planning Policy’ (“SPP”) introduced a presumption in favour of development which contributes towards sustainable development (known as the “Presumption”). Where a local authority has a shortfall in its five-year effective housing land supply, or the development plan is out of date, the Presumption is a significant material consideration.

The language used in SPP is similar, but not identical, to the National Planning Policy Framework (”NPPF”) in England, where it is recognised that a shortage in housing land results in a “tilted balance” in favour of the grant of planning permission. 

There has been an increasing debate around whether a “tilted balance” applies in similar cases in Scotland.

Application of the Presumption

There was no dispute between Gladman Developments and Scottish Ministers that Inverclyde Council had a shortfall in its five-year effective housing land supply.

However, in refusing the planning appeal, the Reporter did not apply the Presumption because she did not consider the appeal site to be one which contributed towards sustainable development.

The key issue in the challenge was whether the tilted balance applies in Scotland in a similar fashion to England. The question was critical to the planning case, as it has been in many others.

The approach adopted by the Reporter in the planning appeal, which was supported by Scottish Ministers during the judicial appeal, was that the Presumption was only engaged where a site was first found to contribute towards sustainable development. This created a two-stage approach, effectively making sustainability a pre-qualification for the Presumption to be applied. Gladman Developments argued that the Presumption and tilted balance should be applied as a result of the shortfall in housing land supply, similar to the approach in the NPPF.

The Inner House of the Court of Session upheld Gladman’s appeal and held that the Reporter’s two stage approach was not a correct application of SPP.

Following on from previous case law, including the 2019 decision in Gladman Developments v Scottish Ministers, the Court held that where the Presumption is a significant material consideration, the adverse impacts of the proposed development must “significantly and demonstrably” outweigh the Presumption before an application or appeal should be refused. “This is part of the equation for determining whether a development is, in overall terms, sustainable. It is not an exercise which is undertaken after a determination on sustainability has taken place.

On the question of contributions towards sustainable development, the Court stated that: “A housing development which will remedy, to some extent, a housing shortage is something which almost inevitably ‘contributes to sustainable development”. 

Whether or not a proposed development is ultimately one that contributes to sustainable development is a question of planning judgement, “… but it involves the use of the tilted balance.

On the application of the tilted balance, the Court explained (paragraph 47) that:

“The starting point ought, on the contrary, to have been that there was a presumption in favour of this development because, inter alia, it provided a solution, at least in part, to the housing shortage. Thereafter, the question was whether the adverse impacts, notably the other policies in the development plan, “significantly and demonstrably outweighed” the benefits of the development in terms of the housing shortage and the economic gain.”  

The Court therefore allowed the appeal, and quashed the Reporter’s decision. The planning appeal will now be remitted to the Scottish Ministers for re-determination.

Calculation of the Housing Land Supply

The Court also agreed with Gladman Developments that, when calculating whether an adequate housing land supply was being provided, the assessment should be made against the local authority’s housing land requirement (“HLR”) rather than its housing supply target (“HST”).

The HST is set for each local authority area based on a Housing Need and Demand Assessment. SPP then requires local authorities to increase the HST by a margin of 10 per cent to 20 per cent to identify the HLR – the purpose of which is to secure a generous housing land supply.

The Court explained that it is the HLR to which regard should be had when the level of the shortfall is being considered. “The greater the shortage, the heavier the weight which tilts the balance will be.

Conclusion

There has been a clear difference between the development industry and local authorities and some Reporters on how paragraph 33 of SPP should be applied in individual cases. This decision provides further clarity on how the SPP Presumption applies both where there is a shortfall in the five- year effective housing land supply and where a development plan is more than five years old.

The Court’s judgment, and quashing of the appeal, should put planning decision-makers on notice as to the weight to be attached to SPP, and the proper application of the Presumption and the tilted balance.

If you have a proposed development where housing land supply and the application of the Presumption is of importance, we would be happy to discuss it with you.

Key contact

Michael Barlow

Michael Barlow Partner

  • Head of Environment
  • Head of Water
  • Head of ESG

Subscribe to news and insight

Burges Salmon careers

We work hard to make sure Burges Salmon is a great place to work.
Find out more