The Procurement Bill: Recent changes following exit from House of Commons Committee Stage

This website will offer limited functionality in this browser. We only support the recent versions of major browsers like Chrome, Firefox, Safari, and Edge.
The Procurement Bill is nearing the end of its passage through Parliament and is expected to become law in Spring 2023.
Draft Secondary Legislation is expected to go out for consultation in the next few months, putting meat on the bones of some important part of the Bill, including the heavily revised procurement notices regime and information to be shared via the online portal. The Cabinet Office’s training offering to Contracting Authorities is heading towards finalisation. The new regime is currently still on course for “go-live” in Spring 2024 (based on current Cabinet Office aspirations communicated at the recent Procurement Reform Conference).
This article highlights four important changes in the current draft Bill against the version that exited the House of Lords. If you are interested in reading a summary of where we have come from, read our previous article on The Procurement Bill: Key changes as it leaves the House of Lords.
There are a number of substantive changes, some made by the Lords and retained, others added by the Commons or reversing changes made in the Lords. Other important changes include clarification of the test for abnormally low tenders (ALTs), and a new provision relating to international trade disputes. However, we focus here on what we think are four key areas of change. By far the most significant change is likely to be the new debarment regime.
We summarise the changes below but you can see a ‘redline’ of the key relevant sections of the draft Bill discussed below by clicking here.
The change here is one example of something wider: the Commons have reversed a number of changes inserted by the Lords, bringing the text of the Bill closer to its original proposed form. A particularly notable aspect of this is Section 13, under which the Government will publish iterations of its National Procurement Policy Statement (NPPS) – setting out its strategic and policy priorities for Government procurement – and Contracting Authorities will be required to “have regard to it” when undertaking acts covered by the Bill.
An insertion by the Lords into the previous draft Bill was that, before publishing its NPPS, the Government had to give “due regard” to high level principles such as promoting the public good, value for money, transparency, integrity, fair treatment and non-discrimination. This has now been removed. What remains is a requirement that the Government must first carry out appropriate consultations and make any necessary changes in view of the responses.
This is an understandable change. Critics of the amendment pointed to the risk of mixing policy – which may change with the Government of the day – and the legal framework of the Bill – which is designed to withstand the test of time. The remaining text of Section 13 strikes a balance which enables the Government of the day to inject current policy into the factors to which a Contracting Authority must have regard, and to update those factors by subsequent revisions to the NPPS.
The “rules of technical specifications” are an important part of constructing a procurement:
Section 56 of the current version of the Bill (which is unlikely to change on this point), now provides that:
These additions bolster existing provisions on equivalence. For example, the Bill already provided that conditions of participation could not “require particular qualifications without allowing for their equivalents”. However, it creates a counterbalance to the calls from various bodies to use the Bill as a driver for the “Buy British” agenda. These provisions also pose a potentially significant burden to a Contract Authority. They must accurately identify whether a UK Standard “adopts an internationally recognised equivalent” (presumably from reading the Standard and/or the literature surround it) and also give clear thought to why they are asking for the UK Standard and therefore which other standards they might consider equivalent in that context. The flipside is that it may promote a greater plurality of bidders.
There are small but important changes to time limits. The core of Section 54 is still the obligation for the Contracting Authority to “have regard to” a range of practical factors when setting time limits (such as the nature of the procurement, its complexity, a need for site visits, and a need for bidders to be able to line up sub-contractors). Nevertheless, the minimum time limits are important, not least for urgent procurements outside of the mechanisms for Direct Award.
The notable additions at Committee stage are special time limits for utilities and non-Central Government contracts. Without these additions, the relevant time limits would be somewhere between 25 and 35 days. However, provision is now made so that there is no minimum period for a procurement of a utilities contract (or contract awarded by a contracting authority that is not a central government authority) which is subject to a “negotiated tendering period”, and a minimum period of merely 10 days where the procurement is only open to “pre-selected suppliers”.
Debarment was a new concept brought in by the draft Bill, and this part of the Bill has now seen something of an overhaul in terms of how bidders can object to their potential inclusion on the Debarment List. In summary, that challenge mechanism for a bidder to avoid being put onto the Debarment List will work much like the current regime for challenging the outcome of procurements, with a standstill period, and the potential for suspension during the challenge. However, the discretionary nature of the suspension from inclusion on the List during the challenge, and the limited remedies available to the challenger, are notable differences.
The Debarment Regime will create a single accessible public Debarment List, maintained by the Government, containing suppliers who (with limited exceptions) will be barred from competing for future covered procurements. The Debarment List will list both “excluded suppliers” (being those to whom a mandatory exclusion ground applies preventing them competing) and “excludable suppliers” (being those to whom a discretionary exclusion ground applies and so may be prevented from competing). Inclusion on the list is therefore potentially highly damaging for the bidding organisation.
Before being placed on the Debarment List, a Minister must first conduct an investigation, giving the relevant supplier notice that they are being investigated and the opportunity to make representations. As part of this process, the supplier may be required to provide relevant documents (in their possession or control) and/or “give such other assistance” that is reasonable in the circumstances. Once the investigation has concluded, a report will be published (subject to national security or public interest concerns) which will include whether and for what reason(s) the supplier will be entered onto (or will be kept) on the debarment list by virtue of a mandatory or discretionary exclusion ground.
The latest changes provide a new process for suppliers to challenge their inclusion on the debarment list:
(a) the public interest in, among other things, ensuring that public contracts are not awarded to suppliers that pose a risk,
(b) the interest of the supplier, including in relation to the likely financial impact of not suspending the decision, and
(c) any other matters that the court considers appropriate.
Given the severe bidding and reputation consequences of entry onto the Debarment List, it is probably right that the Bill should contain interim relief and appeals mechanisms. However, the mechanisms now provided are quite narrow in scope and at the same time have fairly involved processes. The challenge window is small; the available grounds for appeal are limited to mistakes of law and there are no enhanced disclosure provision to ensure the bidders is given from the outset the materials relied on by the Minister in order to mount an effective challenge. The available damages are limited to wasted tender costs.
It will be important for suppliers to act fast if they are notified of an investigation. The representations and documents provided at this stage will be vital in avoiding an adverse report being published. And if a debarment decision cannot be avoided, prompt action and decision-making will become even more important to mitigate and/or reverse the impact. There will be less than eight days to lodge an application for interim relief and only a further 22 days to digest the Minister’s reasons and consider bringing substantive proceedings.
If you found this article helpful, continue to look out for new content on our P.A.T.H (Procurement Act Training and Help) webpage, which is regularly updated to provide insight and assistance for those preparing for the Procurement Bill’s implementation.
This article was written by members of our Chambers Band 1 Ranked Procurement Team: Ian Tucker (Partner), Lloyd Nail (Senior Associate) and David Hine (Associate).